Elite Finishing : HopeWood custom baked on finish
Looking through the top coat booth through the oven
Finishing equipment is all installed
Concrete is poured in finish room. Remainder of warehouse poured on 8/20.
Heating pipes are installed waiting on concrete. 8/18/14
Dow foam is down waiting on radiant heat tubes to be laid.
August 1st
July 1st side
< >
September progress
9/1/14 - global booth install begins 
10/01/14 - finish line installed
11/01/14 - opening day if all inspections are met